King Fahad Medical City, Riyadh.

BMS system installation in OPD and Housing Tower-C
Energy management system and Access Control system in Housing Tower-C.
Installed Energy Management system in the building.
Power Saving in all 380 guest rooms.
RF Locking system
Integration of RF Locking system with Energy Saver.
Commissioning of BMS System
Integration with FAS System.
Interface with KFMC main Server.

Completed Year: 2013, 2014

Beyt Al Maktabiyath, Riyadh.

BMS system installation for all offices in the building.
All Lighting and HVAC control systems.
Integration with CISCO conference system.
Web Access workstation.
Interface with meeting room management system.
Integration with FAS System.
Completed Year: 2011

Holiday Villa Hotel, Madina Munwwarah

-Total room automation(TRA) for 350 rooms.
-Integration with OPERA hotel management system.
-Control of Lighting, HVAC, room service and Blinds.
-Supply and Integration with CISCO IP solutions for telephone, CCTV and Internet.
-Additional Control solution for General Lobby FCU (230 No's) and general Chillers and AHU.
-Workstation Software in reception, Server software in main control room.
-Install and integrate with VING CARD Access control system.
-System implemented: Native BACNet.
Completed Year: 2010

King Khalid Military City- Water Treatment Plants

-Water Treatment Plants, -17 Wells Area, 17 Submersible Pumps with 2 Tanks.
-Level Measurement using VEGA and integrated through Modbus.
- Butterfly Valve actuator installed 800 meter below ground level.
-Fiber network supplied, installed and commissioned for 27,000 meter.
- Workstation Software in WTP and Server software and Integration with 50” LCD screen in CCMS.
-System implemented: Native BACNet.
Completed Year: 2010

Sulaiman Habib Hospital, Riyadh & Qassim

-Complete BMS system in OB-GYNE hospital in Riyadh and General Hospital in Qassim.
- Control of Chillers, AHU and Mechanical pumps, Common FCU’s with BACNet network thermostat, Exhaust Fans and Tanks level monitoring.
- Integration with Hospital call system and public address system for emergency call.
- Workstation Software in maintenance room, Server software in main control room.
- System implemented: Native BACNet.

Completed Year: 2008, 2010

Manar Madina Hotel, Madina Munawwarah.

Control of Chillers, AHU and Mechanical pumps.
Exhaust Fans and Tanks level monitoring.
Integration of CCTV system with BMS.
Workstation Software in maintenance room, Server software in main control room.
Interface with Hotel management systems.
System implemented: Native BACNet.
Completed Year: 2009

Ministry of Justice, Riyadh

Control of Chillers, AHU and Mechanical pumps.
Control and Monitor of all Common FCU’s with BACNet network thermostat.
Control and monitoring of room thermostat in all rooms with BACNet network controller.
Exhaust Fans and Tanks level monitoring.
Interface with Fire Alarm system.
Workstation Software in maintenance room, Server software in main control room.
System implemented: Native BACNet.
Completed Year: 2008

Royal Dyar Hotel, Madina Munawwarah.

- BMS and CCTV system.
- Control of Chillers, AHU and Mechanical pumps,  Exhaust Fans and Tanks level monitoring.
-Control and Monitor of all Common FCU’s with BACNet network thermostat.
- Supply & Install CCTV system & Integration with BMS & Hotel management systems.
- Workstation Software in maintenance room, Server software in main control room.
- System implemented: Native BACNet.

Completed Year: 2008

Al Yamama Boys and Girls College

BMS system installation in both Boys and Girls College.
Energy management system, Access Control System, Lighting and HVAC control systems.
Also includes lighting control in Mosques and Stadium.
Integration with University server system and access through web from anywhere.
Installation and commissioning of Fiber network between buildings.
Integration with Smart Binds system, FAS System.
Installed system: Native BACNet.

Completed Year: 2005, 2008

King Khalid Military City- Chilled Water Plants

-Two Chilled Water Plants.
-8 Chillers with capacity 13000 Tons, 12 Loop Pumps, 10 Primary pumps, 10 Condenser Pumps.
-Monitoring  of  230 Tunnels.
- Cooling Tower Fan  8 units ,  Power Distribution Panel.
- Workstation Software in Chilled Plant and Server software in CCMS.
-Integration with CCTV system in Tunnel Door.
-System implemented: Native BACNet.
Completed Year: 2003

Haql General Hospital, Haql.

Control of Chillers, AHU and Mechanical pumps.
Control and Monitor of all Common FCU’s with BACNet network thermostat.
Exhaust Fans and Tanks level monitoring.
Integration with Hospital call system and public address system for emergency call.
Workstation Software in maintenance room, Server software in main control room.
System implemented: Native BACNet.
Completed Year: 2006